3 weeks (or more) before the targetted date for the change
Prepare all you can to limit what can go wrong on this change.
Prepare tests : what validates that the change is done and didn't break anything.
Estimate the time window needed for the change.
Validation phase
At 2 weeks before
Pre-check what should be done on D-day with Pierre André :
What will be modified
How to test it
The downtime duration requested
During that week, correct what needs to be corrected after this pre-checking with Pierre André
Communication
1 week before
Validate that everything is ready to run the change : GO / NOGO from Pierre André
Send the communication (planned maintenance template link) either by email to Pierre André and all the people affected by the change / the Teams group (eg: ISC Learn Platform)
1 day before
Send a notification to remind of the change tomorrow
Implementation
On D-day
Go on Infomaniak's dashboard > VPS > Hannibal > Snapshot to take a snapshot on the VM data only (Hannibal for ISC Learn) : The system snapshot feature at Infomaniak seems broken (repeated failed tests from Hasdrubal)
NOTE : the data snapshot takes about 2h30 on Hannibal