| - | # Change Management | + | # Change Management |
| Line 9: | Line 9: | ||
| - | ### Production scope : | + | ### Production scope |
| - The [[ https:// | - The [[ https:// | ||
| Line 17: | Line 17: | ||
| ### Preparation | ### Preparation | ||
| - | #### 3 weeks (or more) before the targetted date for the change | + | #### 3 weeks (or more) before the targetted date for the change |
| - Prepare all you can to limit what can go wrong on this change. | - Prepare all you can to limit what can go wrong on this change. | ||
| - Prepare tests : what validates that the change is done and didn't break anything. | - Prepare tests : what validates that the change is done and didn't break anything. | ||
| Line 24: | Line 24: | ||
| ### Validation phase | ### Validation phase | ||
| - | #### At 2 weeks before | + | #### At 2 weeks before |
| - Pre-check what should be done on D-day with Pierre André : | - Pre-check what should be done on D-day with Pierre André : | ||
| - What will be modified | - What will be modified | ||
| Line 35: | Line 35: | ||
| #### 1 week before | #### 1 week before | ||
| - | : | ||
| - Validate that everything is ready to run the change : GO / NOGO from Pierre André | - Validate that everything is ready to run the change : GO / NOGO from Pierre André | ||
| - Send the communication ([[planned maintenance template link]]) either by email to Pierre André and all the people affected by the change / the Teams group (eg: ISC Learn Platform) | - Send the communication ([[planned maintenance template link]]) either by email to Pierre André and all the people affected by the change / the Teams group (eg: ISC Learn Platform) | ||
| - | #### 1 day before | + | #### 1 day before |
| - Send a notification to remind of the change tomorrow | - Send a notification to remind of the change tomorrow | ||
| ### Implementation | ### Implementation | ||
| - | #### On D-day : | + | #### On D-day |
| - | - Send a st | + | - Go on Infomaniak' |
| - | a | + | - **NOTE : the data snapshot takes about 2h30 on Hannibal** |
| - | rt notification at the beginning ([[Start template link]]) | + | - Send a start notification at the beginning ([[Start template link]]) |
| - Implement the change | - Implement the change | ||
| - Run tests | - Run tests | ||
| - | #### If all is fine in the change window | + | #### If all is fine in the change window |
| - Send the end of maintenance notification ([[End of maintenance template link]]) | - Send the end of maintenance notification ([[End of maintenance template link]]) | ||
| - | #### If there is an issue in the change window | + | #### If there is an issue in the change window |
| - Continue debugging until at most 30min before the end of maintenance window | - Continue debugging until at most 30min before the end of maintenance window | ||
| - Either it is solved and you can send the end of maintenance notification ([[End of maintenance template link]]) | - Either it is solved and you can send the end of maintenance notification ([[End of maintenance template link]]) | ||
| - or if the issue is not solved 30 min before the end : send a new notification with the estimated extra delay to fix the issue. | - or if the issue is not solved 30 min before the end : send a new notification with the estimated extra delay to fix the issue. | ||
| - | - if the issue will take way longer than acceptable extra time to fix, then send a incident notification ([[Incident start template link]]) and go to the [[administratif: | + | - if the issue will take way longer than acceptable extra time to fix, then send a incident notification ([[Incident start template link]]) and either try to fix with files from the [[ https:// |
| + | - **Warning : it takes about 1h to restore a data snapshot** | ||
| + | - Prepare to go on with the [[administratif: | ||